REDUR Guarromán

REDUR Guarromán During the first half of July 2022, the new establishment of the multinational REDUR in the town of Guarromán, Jaén, came into operation. GMD Solutions carried out all the work of project drafting, project management, and management of licenses and legalizations with the different institutions: town hall, the Industrial delegation, and the Junta…

Self-consumption at Bálamo restaurant

Self-consumption at Bálamo restaurant During the fourth quarter of 2020, a photovoltaic system for self-consumption was installed in the Bálamo restaurant in the Ensanche Sur neighborhood of Alcorcón (Madrid) with a total installed power of 120.4kWp. GMD Solutions, which had already drawn up all the installation projects for the new establishment, designed and managed the…

REDUR Vitoria

REDUR Vitoria As part of its ambitious expansion plan, the multinational logistics company REDUR put into operation last March its state-of-the-art dispatch center in the city of Vitoria. GMD Solutions drafted the projects and carried out the Project Management and management of licenses and legalizations with the different institutions: the city council, the delegation of…

Decathlon City Gijón

Decathlon City Gijón On January 10, 2022, the new Decathlon City store was opened in Gijón (Asturias). It is a relocation to larger premises in the same square Seis de Agosto. The new store has a total area of 489 m² distributed over 3 floors: a ground floor through which the store is accessed, with…

Luxury home – Sierra de Madrid

Luxury home – Sierra de Madrid In the first semester of 2021, GMD Solutions executed the BIM (Building Information Modeling) consulting and calculation of facilities and structure of the project of a luxury home in the Sierra de Madrid. Paloma Cañizares’ Architect Studio, developed the entire project at the architectural level, while our GMD team…

REDUR Coruña

REDUR Coruña Between March and August 2021, GMD Solutions carried out the integral management of the project for the construction of a delivery warehouse (Cross Docking type) in the town of Culleredo (A Coruña). The project, promoted by our client REDUR, was developed out and executed entirely with BIM methodology, achieving a considerable optimization of…

Logroño Bus Station

Logroño Bus Station GMD Solutions participated between the last quarter of 2017 and the whole of 2018 in the execution project of Logroño’s new bus station. Specifically, the Riojan UTE Agua y Jardín-Ismael Andrés-Vías y Construcciones was the contractor in charge of executing the works and hired the services of a production manager from the…